An aerospace drawing is bought on its evidence. The alloy must be provable to a heat number and a mill certificate, the machining route must be repeatable, every critical dimension must carry inspection data, and the whole chain has to survive an audit months after the parts landed. When you source aerospace parts from a precision machining factory in China, the first question is not whether the tolerance can be held - it is whether the factory can prove that it held it.
The answer to plan around is straightforward. Most aerospace brackets, housings, and fittings are prismatic parts whose features sit on accessible faces, which puts them in the normal working range of a precision machining floor. What makes them aerospace parts is not exotic machining; it is the material contract and the documentation contract. Nail those two and the machining is a precision metal-cutting job like any other; skip them and no capability claim on the website will save the program.
1. What changes when a part is headed into an aerospace program?
Geometry is rarely what changes. A commercial bracket and an aerospace bracket can be cut with the same toolpaths on the same machine class. What changes is the obligation around the part: every material claim must be verifiable, every critical dimension must carry inspection evidence, every process change must be documented, and the record must survive reconstruction after shipment. Aerospace sourcing is evidence management with machining attached.
That reframes supplier selection. A factory that machines well but treats paperwork as optional is a liability on an aerospace program, because the failure mode is the record that cannot be produced when the auditor asks. A factory with tidy documents but ordinary capability fails the part instead. Both halves must be present, and a buyer should test them in that order - evidence first, then geometry.
It also changes the quoting conversation. Aerospace drawings carry revision control, material condition, and inspection frequency requirements that all carry cost and lead time. A supplier that quotes an aerospace drawing without asking about the FAI format, the documentation package, or the inspection frequency is not quoting the job you are buying. The questions a factory asks are the first evidence of whether it understands the program.
2. Which aerospace alloys and tempers should the drawing name?
The aerospace material list is short, and the condition attached to each grade is where sourcing errors start. Aluminum appears as 6061-T6 for general structure and 7075-T6 for higher loads, with -T7351 chosen where stress-corrosion resistance matters. Stainless shows up as 17-4PH and 15-5PH, machined in the annealed or solution-treated condition and aged after machining to the specified strength. Titanium is dominated by Ti-6Al-4V, with the ELI variant for fracture-critical parts. Inconel 718 covers the hot sections, and PEEK covers the polymer corners where weight and chemical resistance beat metal.
Each entry changes the machining route in a specific way. 7075 machines harder and costs more than 6061. Aged stainless needs heat treatment sequenced between roughing and finishing. Titanium is slow, expensive, and demanding on tooling. Inconel is the hardest on every axis - cost, cycle time, and tool wear. PEEK is a polymer with polymer behavior, cut with different tooling and feeds entirely. The drawing that names grade and condition is the drawing that can be quoted; the drawing that leaves them open makes the shop guess, and the guess is priced in.
For a precision machining route specifically, the material decides how far a part stays on the economical side of the floor. A 6061 bracket with all features on one face is fast and cheap. A 17-4PH fitting with features on several faces may run with indexing or a second setup, and the material and the setups both add cost. The material choice and the process choice are one decision, and aerospace buyers should make it deliberately rather than inherit it from an old drawing.
3. What tolerances are realistic on aerospace parts - and where should they sit?
Aerospace parts are tight where function demands and ordinary elsewhere. Bores that carry bearings, faces that seal, and features that locate other components carry the critical callouts, verified against a datum reference frame on a CMM under the quality system. Everything else runs to general tolerance, because a wall of tight dimensions buys inspection hours without buying function.
What precision machining holds is well established: ±0.003 mm on milling and turning, ±0.002 mm on grinding, with capability targets such as Ppk ≥ 1.67 at the initial study on key characteristics and Cpk ≥ 1.33 on general characteristics. Capability is reported per characteristic: every report names the feature, its tolerance band, the sample size, the sigma method, and the study window. The realistic question is the geometry around each callout. A tight bore in 6061 is routine; the same bore in a thin-walled Inconel housing is a process-development project. A tight flatness on a large titanium plate fights residual stress and temperature. The tolerance is only as honest as the material and the process behind it.
The inspection discipline matters as much as the number. On an aerospace drawing, review which critical tolerances cross machining steps or setups, because those are the features whose verification depends on the datum scheme and the measurement method. Ask the factory how the critical callouts will be measured and documented before the first article, not after the parts are in the box.
4. What material documentation should you request - and what is realistic to receive?
The baseline document is the material certificate: heat number, grade, condition, and the chemical and mechanical values from the mill or distributor, naming the specification the material was produced to. On aerospace work it should arrive with the parts or before them. A certificate that names a different grade, carries an unreadable heat number, or shows values that miss the drawing requirement is a flag, not a document.
What separates a serious machining factory is the step before the certificate is filed: verifying the delivered lot against the certificate, so the heat stated is the heat machined. This incoming check catches substituted or mixed alloys, and it is the most valuable material control a buyer can insist on, because no downstream inspection can detect that the wrong alloy was in the machine. Ask how incoming stock is confirmed and what happens when a check fails.
Be realistic about what to expect. The mill certificate and the verification record are standard; the factory re-certifying material it did not produce is not. If the program demands heat-level traceability across multiple parts, say so at quoting, because segregated lots and heat-level records change how the run is planned and priced.
5. How do first-article inspection and FAI work on a sourced job?
A first-article inspection verifies every characteristic on the drawing against the approved configuration, usually on the AS9102 form or the customer's equivalent. The machining supplier produces it at the first article, with the dimensional data behind each characteristic and the drawing revision it was measured against. This is where the tolerance callouts become evidence instead of intentions.
On a sourced job, the FAI is only as good as its review. A document arriving by email is a claim; the review that checks the datum scheme, the sampling, and the measurement method against the drawing is the control. For critical features the CMM data should be readable - which datums were used, how the feature was aligned, and what was measured - not a pass/fail stamp with no numbers behind it.
Sequence the FAI before production, not after. A supplier that machines the full run and produces the FAI afterward has turned first-article inspection into last-article confirmation. The professional sequence is first article, full inspection, FAI issued, buyer review, then release of the remaining quantity. That gate is what de-risks a sourced aerospace part, and a supplier's willingness to hold it predicts how the rest of the relationship runs.
6. Which certificates should the machining factory hold, and where does AS9100 sit?
Certification is the cheapest pre-qualification a buyer can run, because it proves a documented, externally audited quality system exists. For a build-to-print machining factory serving aerospace through an upper tier, the meaningful certificates are ISO 9001:2015 and IATF 16949:2016 (product design excluded) for the quality system, plus ISO 14001:2015 for environmental management. All three should be current, and their scope lines should cover machining.
AS9100 is the aerospace quality standard, and it sits one step up the chain. If your contract requires machining at an AS9100-certified site, nothing else substitutes, and the certificate must be verifiable with the registrar. But much aerospace machining flows through primes and tiers that hold AS9100 and release work to build-to-print suppliers under their control plans - and in that structure, a factory certified to ISO 9001 and IATF 16949 (product design excluded) can carry the machining while the upper tier owns the aerospace system obligation.
The buyer's job is to know which structure applies before quoting. Ask whether the program requires AS9100 at the machining site or accepts an upper-tier control plan, and ask the supplier to state its certification scope plainly. A certificate number on a website is marketing; a current certificate with a matching scope, confirmed against the registrar, is evidence.
7. What should the inspection and evidence package contain when the parts land?
When aerospace parts arrive, the part and its package should tell the same story. At minimum the package carries the dimensional report for the critical characteristics, the material certificate, and a statement of conformity to the drawing revision. A serious program adds the FAI package, SPC charts where key characteristics were process-monitored, and a record of any non-conformance and its disposition.
Read the package as a chain, not a pile of papers. The material certificate should match the heat on the traveler; the dimensional report should reference the same drawing revision as the FAI; the SPC charts should name the same characteristics as the critical callouts. Gaps between documents are where sourcing risk hides, and reconciling the package before payment catches more problems than inspecting the parts alone.
Two practical checks make the package useful. Confirm the drawing revision on every document matches the revision you released - a package built against an outdated revision is worse than none. And file the evidence against the part identity rather than the purchase order, so a specific lot or serial can be pulled months later. That is the traceability an auditor actually tests.
8. How do you de-risk the first aerospace order before scaling to volume?
The first order is a qualification exercise wearing a purchase order. Use it to test what a brochure cannot: whether the factory machines the drawing as released, produces inspection data that reconciles, ships the documentation with the parts, and answers hard questions without friction. The evidence from that order, not its price, decides whether the program scales.
Run the qualification in stages. Send a representative part with real critical callouts and demand the full package. Have the FAI reviewed independently - by your own engineer or a third-party inspector who knows aerospace drawings. Verify the certificates against their registrars, and confirm the incoming material check happens the way it was described. If the program justifies it, audit the factory in person or by live video before the production release.
A supplier that clears that bar on the first order earns the volume on evidence. One that clears it only on price will spend the difference later, in rework, expediting, or an audit finding no tolerance band can cure. Aerospace sourcing is a long game played one qualification at a time - and the buyer who treats the first order as a test is the one whose production runs arrive on evidence, not on hope.
Frequently Asked Questions
Can a Chinese precision machining factory make aerospace-grade parts?
Yes, for the prismatic brackets, housings, and fittings that make up most machined aerospace content. The axis count and material are process decisions; what makes a part aerospace-grade is the documentation obligation around it. A build-to-print factory certified to ISO 9001:2015 and IATF 16949:2016 (product design excluded) can serve under an upper tier's AS9100 control plan, or directly where the contract accepts it.
Which aerospace alloys and tempers should the drawing name?
Aluminum 6061-T6 and 7075-T6 (often -T7351), stainless 17-4PH and 15-5PH in the aged condition, titanium Ti-6Al-4V and its ELI variant, Inconel 718 for hot sections, and PEEK where weight and chemical resistance win. Every grade must appear with its condition, because the condition sets the process route, any heat-treatment step, and the price.
What tolerances should an aerospace drawing request?
Tight control belongs on the features that carry load, seal, or locate; general tolerances belong everywhere else. Precision milling and turning hold ±0.003 mm and grinding reaches ±0.002 mm, with capability targets such as Ppk ≥ 1.67 at the initial study on key characteristics and Cpk ≥ 1.33 on general characteristics. Capability is reported per characteristic: every report names the feature, its tolerance band, the sample size, the sigma method, and the study window. Blanket-tight drawings multiply inspection hours without adding function, so concentrate the criticals and let the rest breathe.
What material documentation should arrive with an aerospace order?
A material certificate naming the heat, grade, condition, and the mill's chemical and mechanical values is the baseline, arriving with the parts or before them. The control that matters behind the paper is verification of the delivered lot against the certificate, so the heat stated is the heat machined. Ask how incoming material is checked, because a certificate alone proves only that a document exists.
Who should produce the first-article inspection on a sourced aerospace part?
The machining supplier produces the FAI against the approved drawing revision - typically following AS9102 or the customer's equivalent - with the measurement data behind every characteristic. The buyer or an independent inspector reviews it before the production release. That review gate, not the document itself, is what retires the sourcing risk on the first order.
Which certificates should the machining factory hold?
For a build-to-print precision machining factory, ISO 9001:2015, IATF 16949:2016 (product design excluded), and ISO 14001:2015 are the meaningful ones, current and with scopes covering machining. AS9100 sits one step up: where your contract requires it at the machining site, only a current AS9100 certificate satisfies it; where an upper tier holds it and flows a control plan down, the ISO 9001 and IATF 16949 (product design excluded) factory can serve under that oversight.
What should the evidence package contain when the parts land?
The dimensional report on critical characteristics, the material certificate, and a statement of conformity to the drawing revision are the minimum. A serious program adds the FAI package, SPC charts on key characteristics, and any non-conformance record. Reconcile the package against the drawing revision and the part identity, because gaps between documents are where sourcing risk hides.
How do you de-risk the first aerospace order before scaling?
Treat the first order as a qualification run: send a representative drawing, require the full documentation package, and have the FAI reviewed independently before release. Confirm the certificates against their registrars, verify the incoming material check, and audit the factory in person or by live video before production. A supplier that clears that bar on evidence earns the volume.